Richard (our camp caretaker) and I are making preparations for the installation of electricity to the twelve sleeping cabins this week. On Saturday we'll be moving a trencher to camp and begin cutting trenches for the installation of underground power lines.
Next week, we're scheduled to install a 30' power pole for the main line off the transformer and a meter post as well.
This weekend we have a work crew of approximately 14 working on brush clearing. Anyone who wants to join us for the weekend or just for the day is welcome.